Task #3183
MNDeployment #3182: ORNL Data Centers member nodes
Initial contact with CDIAC
100%
Description
During the Aug 2012 CCIT meeting, it was decided that contact should be made with CDIAC to determine their interest and viability in becoming a DataONE member node.
This task is to track that initial contact.
History
#1 Updated by Mike Frame almost 12 years ago
- Target version set to Deploy by end of Y5Q2
#2 Updated by Bruce Wilson almost 12 years ago
I've discussed this some with Tom Boden. I need to follow-up to see what further discussion there was about this at the Climate Change Science Institute (CCSI) advisory board meeting last week. Note that Mike Frame and Sara Graves are both on the CCSI Advisory Board (Sara is the current chair).
#3 Updated by Bruce Wilson over 11 years ago
- Target version changed from Deploy by end of Y5Q2 to Deploy by end of Y5Q4
#4 Updated by Bruce Wilson over 11 years ago
- Target version deleted (
Deploy by end of Y5Q4)
#5 Updated by Bruce Wilson about 11 years ago
- % Done changed from 0 to 100
- translation missing: en.field_remaining_hours set to 0.0
- Status changed from New to Closed
Met. DOE BER is open to CDIAC becoming a Tier 1 MN, as long as there is minimal cost to the project, DataONE correctly reflects how much of the CDIAC content is available through DataONE, and that the mutable content issue is resolved.
#6 Updated by Laura Moyers almost 9 years ago
- Priority changed from Normal to Low
- Estimated time set to 0.00
Deferred indefinitely (see MNW notes 2/22/16)