Project

General

Profile

Task #4139

MNDeployment #3708: Minnesota Population Center

Touch base with MPC to see who to have in follow-up telecon in mid- to late-November

Added by Bruce Wilson over 10 years ago. Updated over 9 years ago.

Status:
Closed
Priority:
Normal
Assignee:
Target version:
Start date:
2013-10-29
Due date:
2013-11-04
% Done:

100%

Story Points:
Sprint:

Description

Following up on 2013-10-29 telecon with MPC (see epad at http://epad.dataone.org/MPC-and-DataONE), touch base with Alex and Tracy to see who needs to be in the next call and when to have that call

History

#1 Updated by Bruce Wilson over 10 years ago

  • Status changed from In Progress to Closed
  • % Done changed from 0 to 100
  • translation missing: en.field_remaining_hours set to 0.0

Tentatively scheduled for 11/7; may need to adjust. Good email discussion of what's involved in DataONE implementation. Going down the route of OAI-PMH with the (as yet unbuilt) Slender Node looks to be the most attractive option.

#2 Updated by Laura Moyers over 9 years ago

  • Target version changed from Deploy by end of Y5Q4 to Deploy by end of Y1Q1

#3 Updated by Laura Moyers over 9 years ago

  • Target version changed from Deploy by end of Y1Q1 to Deploy by end of NCTE

#4 Updated by Laura Moyers over 9 years ago

  • Target version changed from Deploy by end of NCTE to Operational

Also available in: Atom PDF

Add picture from clipboard (Maximum size: 14.8 MB)