Start date:
2013-01-07
Due date:
2013-02-25
% Done:
100%
Story Points:
Sprint:
Description
we want to prepare a release of the R client in time for the Feb. CCIT meeting.
The scope/approach for the release is to have a stable, cleaned up version of existing functionality.
need to branch and tag what we have, and make sure to use a stable d1_libclient_java version.
Subtasks
History
#1 Updated by Matthew Jones over 11 years ago
- Project changed from Infrastructure to DataONE R Client
- Category deleted (
d1_client_r) - Assignee changed from Rob Nahf to Matthew Jones
#2 Updated by Matthew Jones over 11 years ago
- Due date changed from 2013-02-02 to 2013-02-22
- Target version changed from 2013.4-Block.1.2 to DataONE R Client 1.0.0
#3 Updated by Matthew Jones over 11 years ago
- Status changed from New to Closed
THe package is released.