Task #7315
/object get blank page on both mn and cn
100%
Description
History
#1 Updated by Skye Roseboom over 9 years ago
- % Done changed from 0 to 30
- Status changed from New to In Progress
#2 Updated by Skye Roseboom over 9 years ago
- % Done changed from 30 to 50
- Status changed from In Progress to Testing
- Assignee changed from Jing Tao to Skye Roseboom
#3 Updated by Skye Roseboom over 9 years ago
The URLs in the description are demonstrating correct behavior as is paging using the 'start' parameter.
Both MN and CN incorrectly display the 'total=0' value when 'count=0' is used = should show total documents count.
https://mn-demo-6.test.dataone.org/knb/d1/mn/v2/object/?count=0
https://cn-dev-ucsb-1.test.dataone.org/cn/v2/object/?count=0
#4 Updated by Skye Roseboom over 9 years ago
- Assignee changed from Skye Roseboom to Jing Tao
- Status changed from Testing to In Progress
- % Done changed from 50 to 30
#5 Updated by Jing Tao over 9 years ago
- Status changed from In Progress to Testing
- % Done changed from 30 to 50
- Assignee changed from Jing Tao to Skye Roseboom
#6 Updated by Skye Roseboom over 9 years ago
The behavior when count=0 works now! Fixed!
There is some slight variation in paging behavior between MN and CN:
https://cn-dev-orc-1.test.dataone.org/cn/v2/object/?count=100&start=100 (shows 101-200)
while:
https://mn-demo-6.test.dataone.org/knb/d1/mn/v2/object/?count=100&start=100 (shows 100-200).
Current production CN behavior:
https://cn.dataone.org/cn/v1/object/?count=100&start=100 (shows 101-200)
#7 Updated by Skye Roseboom over 9 years ago
- % Done changed from 50 to 30
- Assignee changed from Skye Roseboom to Jing Tao
- Status changed from Testing to In Progress
#8 Updated by Jing Tao over 9 years ago
- Status changed from In Progress to Closed
- translation missing: en.field_remaining_hours set to 0.0
- % Done changed from 30 to 100
Actually, the start attribute has the value "100" in both CN and MN returned xml file. But the xslt adds one to that value and renders it to "101".