Per Matt's email, we need to figure out and schedule the hardware setup and move.
- temporary housing
- temporary network connection
- temporary rack config
- North Hall move-in date
- physical datacenter access
- lockable racks options
History
#1 Updated by Nick Outin over 13 years ago
- Status changed from New to In Progress
Arlene told me the move in date would be in November. And the rack models are lockable, we have the same model at NCEAS, but I don't know what their key policy will be.
#2 Updated by Nick Outin almost 12 years ago
- Milestone set to None
The move is scheduled for Jan 7th at 8:30am. I'm going to backup the servers the week before the move, and am currently configuring the switches for the new DC.
#3 Updated by Nick Outin almost 12 years ago
Todo:
- contact furniture services about insurance
- email Kevin our switch/transceiver info
- change air flow direction on all four switches
- figure out how much data needs to be backed up
- create backups of important data
#4 Updated by Nick Outin almost 12 years ago
Verified that our equipment move is covered by UC property insurance.
#5 Updated by Nick Outin almost 12 years ago
Enabled LACP port aggregation for the two fiber uplinks.
#6 Updated by Nick Outin almost 12 years ago
Took a 2TB USB drive to campus, shut down cn-ucsb-1 and started backing it up to the drive.
#7 Updated by Nick Outin almost 12 years ago
- Status changed from In Progress to Closed
- translation missing: en.field_remaining_hours set to 0.0
- % Done changed from 0 to 100
Everything was moved to the North Hall Data Center